Whittemore Ave neighborhood area and North Parking Lots:
- Building 1: Ongoing activities related to interior construction.
- Building 2: Continued construction activity related to both interior and exterior.
- Building 3: Continued construction activity related to both interior and exterior.
- North Parking Lot C: Being prepared for the installation of landscaping
- East Parking Lot: Construction with sidewalk concrete placements and asphalt laying is ongoing
- Building 2 & Building 3 alleyway is being prepped for landscape and hardscape construction
- Gate A is open and sidewalk installation is currently ongoing
- Gate E near the jug handle road has been completed
The temporary Eversource electrical power has been decommissioned for Building 1 and Building 2, while temporary electrical power remains at Building 3.
Some generators continue to run during regular working hours to support various construction activities. No generators are being run off hours.
The public pathways on the west side of the property running from Whittemore Ave down along Parkway Pond to the MBTA Headhouse Plaza have been repaired and updated with lighting.
October Construction Plan: