Utility disconnections along Whittemore Ave will be completed in early October followed by asphalt road repairs.

Other activities along Whittemore Ave will include:

  • Lot C: Utility connections to the field office/job trailer
  • Lot B: Renovations to the small building
  • Building 1: Ongoing activities related to interior construction activity
  • Building 2: Demolition activity of the exterior envelope

The structural demolition of the remaining existing buildings will start in early October. On the southern side of the buildings 1 & 2 , there will be activities related to tent erecting for future soil disturbing work along with sub-surface non-soil disturbing probing for any potential obstructions in the footprint of new building #4.

Any modifications and improvements to the public pathways on the west side of the property running from Whittemore Ave down along Parkway Pond to the MBTA Headhouse Plaza area will also continue throughout the month.