Activities along Whittemore Ave will include:
- New utility connections from the street to the edge of the property
- Building 1: Ongoing activities related to interior construction
- Building 2: Continued demolition activity
Two large tents have been placed in the footprint of Building 3 and will be active with soil disturbing activities. Two large tents have been placed in the footprint of Building 3 and will be active with soil disturbing activities. On the southern side of the buildings 1 & 2 , there will be activities related to tent erecting along with pile driving activities in the footprint of new building #4.
Utility work near the Harvey St. will be ongoing
Any modifications and improvements to the public pathways on the west side of the property running from Whittemore Ave down along Parkway Pond to the MBTA Headhouse Plaza area will also continue throughout the month.