May 2025

Whittemore Ave neighborhood area: · Building 1 will have ongoing activities related to interior and exterior construction. · Building 2 construction activities completed. · Building 3 will continue to undergo construction activity related to both interior and exterior. · Building 2 & Building 3 alleyway landscape installations and hardscape are completed. · East Parking Lot […]

May 2025 Read More »

April 2025

Whittemore Ave neighborhood area and North Parking Lots:• Building 1 will have ongoing activities related to interior and exterior construction.• Building 2 construction activities completed.• Building 3 will continue to undergo construction activity related to both interior and exterior.• Building 2 & Building 3 alleyway landscape installations and hardscape are nearing completion.• East Parking Lot

April 2025 Read More »

March 2025

Whittemore Ave neighborhood area and North Parking Lots: · Building 1 will have ongoing activities related to interior and exterior construction. · Building 2 construction activities for the interior are nearing completion. · Building 3 will have continued construction activity related to both interior and exterior. · Building 2 & Building 3 alleyway landscape installations

March 2025 Read More »

February 2025

Whittemore Ave neighborhood area and North Parking Lots: Winter heaters in Building 3 will continue to run throughout the season. In late October 2024, the Licensing Commission approved our application for a noise ordinance variance.

February 2025 Read More »

January 2025

Whittemore Ave neighborhood area and North Parking Lots: All pile-driving activities onsite, including Building 5 and the Garage, have been completed. Winter heaters in Building 3 will continue to run throughout the season. In late October 2024, the Licensing Commission approved our application for a noise ordinance variance.

January 2025 Read More »

November & December 2024

Whittemore Ave neighborhood area and North Parking Lots: Pile-driving activities are ongoing in Building B5’s and the Garage’s footprint. This will use a combination of vibratory and impact methods. A pile foundation is a series of steel beams inserted into the ground to transmit loads to a lower subsoil level. A vibratory hammer is a

November & December 2024 Read More »

October 2024

Whittemore Ave neighborhood area and North Parking Lots: The temporary Eversource electrical power has been decommissioned for Building 1 and Building 2, while temporary electrical power remains at Building 3. Some generators continue to run during regular working hours to support various construction activities. No generators are being run off hours. The public pathways on

October 2024 Read More »

July 2024

Whittemore Ave neighborhood area and North Parking Lots: Building 4 excavation in clean excavation has been complete and surrounding hardscape is ongoing. The temporary Eversource electrical substation near Harvey Street is active and provides temporary construction power throughout the site. Temporary overhead electrical lines and poles are installed throughout the site to distribute electricity.  Construction

July 2024 Read More »

June 2024

Whittemore Ave neighborhood area and North Parking Lots: Building 4 open excavation in clean soils will be ongoing in the footprint of the building for utilities. The temporary Eversource electrical substation near Harvey Street is active and provides temporary construction power throughout the site. Temporary overhead electrical lines and poles are installed throughout the site

June 2024 Read More »

May 2024

Whittemore Ave neighborhood area and North Parking Lots: Building 4 open excavation in clean soils will be ongoing in the footprint of the building for utilities. The temporary Eversource electrical substation near Harvey Street is active and provides temporary construction power throughout the site. Temporary overhead electrical lines and poles are installed throughout the site

May 2024 Read More »