Uncategorized

October 2022

Utility disconnections along Whittemore Ave will be completed in early October followed by asphalt road repairs. Other activities along Whittemore Ave will include: The structural demolition of the remaining existing buildings will start in early October. On the southern side of the buildings 1 & 2 , there will be activities related to tent erecting for […]

October 2022 Read More »

September 2022

As of August 29th, the main construction area between Whittemore Ave and the MBTA Headhouse will be secured to isolate the public from the construction zone. The traffic pattern changes to Whittemore Ave will be completed by early September, but there will still be some road excavations for utility disconnections.   Other activities along Whittemore Ave will

September 2022 Read More »