Nara Lee

May 2023

Whittemore Ave neighborhood area and North Parking Lots: Large white tents #1 and #2 are in the footprint of Building 3 and will be active with soil disturbing activities.  Large white tent #3 is currently in the footprint of Building 4 and will be active with soil disturbing activities.  Large white tent #4 has been …

May 2023 Read More »

April 2023

Whittemore Ave neighborhood area and North Parking Lots: Large white tents #1 and #2 are in the footprint of Building 3 and will be active with soil disturbing activities.  Both tents have recently been shifted east.  Large white tent #3 has been place in the footprint of Building 4 and will be active with soil …

April 2023 Read More »

March 2023

Whittemore Ave neighborhood area and North Parking Lots: Large white tents #1 and #2 have been placed in the footprint of Building 3 and will be active with soil disturbing activities.  Both tents will be shifted east before end of the month.  Large white tent #3 has been place in the footprint of Building 4 …

March 2023 Read More »

February 2023

Activities along Whittemore Ave will include: Two large tents have been placed in the footprint of Building 3 and will be active with soil disturbing activities. Two large tents have been placed in the footprint of Building 3 and will be active with soil disturbing activities.  On the southern side of the buildings 1 & …

February 2023 Read More »

January 2023

Activities along Whittemore Ave will include: The structural demolition of remaining existing buildings has begun. On the southern side of the buildings 1 & 2, there will be activities related to tent erecting for future soil disturbing work along with sub-surface non-soil disturbing probing for any potential obstructions in the footprint of new building #4. Smaller …

January 2023 Read More »

December 2022

Activities along Whittemore Ave will include: The structural demolition of remaining existing buildings has begun. On the southern side of the buildings 1 & 2, there will be activities related to tent erecting for future soil disturbing work along with sub-surface non-soil disturbing probing for any potential obstructions in the footprint of new building #4. Smaller …

December 2022 Read More »

November 2022

Activities along Whittemore Ave will include: The structural demolition of remaining existing buildings has begun. On the southern side of the buildings 1 & 2, there will be activities related to tent erecting for future soil disturbing work along with sub-surface non-soil disturbing probing for any potential obstructions in the footprint of new building #4. Smaller …

November 2022 Read More »

October 2022

Utility disconnections along Whittemore Ave will be completed in early October followed by asphalt road repairs. Other activities along Whittemore Ave will include: The structural demolition of the remaining existing buildings will start in early October. On the southern side of the buildings 1 & 2 , there will be activities related to tent erecting for …

October 2022 Read More »

September 2022

As of August 29th, the main construction area between Whittemore Ave and the MBTA Headhouse will be secured to isolate the public from the construction zone. The traffic pattern changes to Whittemore Ave will be completed by early September, but there will still be some road excavations for utility disconnections.   Other activities along Whittemore Ave will …

September 2022 Read More »