Alewife Headhouse Plaza

10/19/2026 – 3 Week Look Ahead

Week 1 (10/19/26 – 10/23/26)

  • Site on hold waiting for reworked work plans approval for concrete work plan

Week 2 (10/26/26 – 10/30/26)

  • Site Lighting & Light Bases
    • Concrete pours for site lighting bases.
    • Trade: Margarite
    • Estimated crew: 10 workers
    • Noise Impact: Moderate
  • Curb/Basecoat
    • Continue curb and basecoat installation work.
    • Trade: Welch
    • Estimated crew: 5 workers
    • Noise Impact: Moderate
    • Install bike racks.
    • Trade: Blue Bike
    • Estimated crew: 4 workers
    • Noise Impact: Minimal

Week 3 (11/2/26 – 11/6/26)

  • Complete any remaining:
    • Site lighting and light bases.
    • Curb/basecoat work.
    • Bike rack installation.