10/19/2026 – 3 Week Look Ahead
Week 1 (10/19/26 – 10/23/26)
- Site on hold waiting for reworked work plans approval for concrete work plan
Week 2 (10/26/26 – 10/30/26)
- Site Lighting & Light Bases
- Concrete pours for site lighting bases.
- Trade: Margarite
- Estimated crew: 10 workers
- Noise Impact: Moderate
- Curb/Basecoat
- Continue curb and basecoat installation work.
- Trade: Welch
- Estimated crew: 5 workers
- Noise Impact: Moderate
- Install bike racks.
- Trade: Blue Bike
- Estimated crew: 4 workers
- Noise Impact: Minimal
Week 3 (11/2/26 – 11/6/26)
- Complete any remaining:
- Site lighting and light bases.
- Curb/basecoat work.
- Bike rack installation.