Whittemore Ave neighborhood area:
- Building 1 will have ongoing activities related to interior construction.
- Building 2 construction activities completed.
- Building 3 is nearing completion of construction activity related to both interior and exterior.
- East Parking Lot landscape and hardscape activities completed and fence removed.
- Promenade will continue site preparation work for landscape and hardscape installation.
- Whittemore Ave will have ongoing isolated roadwork and Jersey Barriers have been removed.
- North Parking Lots activity for setting up a laydown and storage area for the Whittemore Ave Utility Project.