May 2025

Whittemore Ave neighborhood area:

· Building 1 will have ongoing activities related to interior and exterior construction.

· Building 2 construction activities completed.

· Building 3 will continue to undergo construction activity related to both interior and exterior.

· Building 2 & Building 3 alleyway landscape installations and hardscape are completed.

· East Parking Lot will have ongoing landscape and hardscape installations.

· Promenade will have ongoing site preparation work for landscape and hardscape installation.

· Whittemore Ave will have ongoing isolated utility and roadwork.